What is Reorder point?
The reorder point (ROP) is the exact unit inventory threshold at which you must place a new purchase order with your manufacturer so the replenishment shipment arrives just before you dip into safety stock: (average daily sales × total lead time in days) + safety stock.
Example
Selling 20 units per day with a 35-day door-to-door lead time (700 units of lead-time demand) and 80 units of safety stock gives a reorder point of 780 units. The day your sellable + inbound inventory hits 780, you wire the deposit for your next PO.
Why it matters
Guessing when to reorder causes either expensive air-freight emergencies (when you order too late) or tied-up cash and aged storage fees (when you order too early). Get your exact ROP and days-until-next-order countdown in the Reorder Point Calculator.
Calculate Reorder point (Reorder Point Calculator)
Safety stock and when to reorder
Test yourself · Card 1 of 3
0 known · Full deck ›What is reorder point?
Tap to reveal the answerThe exact unit inventory level that triggers your next supplier purchase order: (average daily unit sales × lead time in days) + safety stock.
Next related term: Safety stock →
Frequently asked questions
Q1How do I calculate a reorder point?
Q2What lead time should I use?
Related terms
Safety stock
Buffer inventory held above expected lead-time demand to prevent stockouts from sales spikes or supplier/freight delays: Z-score × daily sales standard deviation × √lead time.
Lead time
The total calendar days from placing a supplier purchase order until the inventory is checked in and sellable — including production, ocean/air transit, customs clearance and warehouse receiving.
Read more in our guide: Safety Stock and Reorder Point: When to Reorder Inventory